  1. In Drawing Manager, open the project for which you want to view the status.

  2. Click Project > Project Status.

  3. In the Smart P&ID project status area, ascertain the current status of your project with respect to the plant.

    A check mark denotes the current status. Possible statuses include Active, Completed, Merged, and Canceled.

  4. Do any of the following to change the status of your project:

    • To change an active project to completed, click Complete Project. This command is available only when the initial project status is Active.

      When you change the project status to Completed, all the drawings in the project are verified for checking into the plant. You can verify each drawing separately if you want to. For more information, see Verify a Drawing for Checkin.

    • To change a completed project back to active, click Return to Active.  This command is available only when the initial project status is Completed.

    • To merge a completed project into the plant, click Merge Project.  This command is available only when the initial project status is Completed.

    • To cancel an active project, click Cancel Project.

  • If the plant is registered, click Refresh Status on the Project Status dialog box to update the SmartPlant project status display.

  • In SmartPlant Foundation, the Complete Project, Return to Active, and Merge Project options are not available unless the SmartPlant project status is also Active. The Cancel Project option is not available unless the SmartPlant project status is also Canceled.