This procedure allows you to update the project schedule enterprise calendars.
-
Navigate to Admin > Projects Admin > Project Schedule Admin.
-
Click the Calendars tab.
-
Click the Insert Row icon.
-
Type in the Calendar ID.
-
Type in the Calendar Name.
-
Type in the Timezone.
-
Type in the Start Hour and Start Minute of the project schedule.
-
Type in the project Duration.
-
Select the required work day check box to select the working days in a week.
-
Click the Save icon.