Follow the procedure below to view the submitted and partially approved budget for the selected project.

  1. Navigate to Admin > Projects Admin > Workflow Admin.

  2. At the top of the screen, in the green parameter bar, click the Project ellipsis to select the required projects.

  3. Click the Budget tab. The submitted and partially approved budgets appear.