The Manual Factor amount can be updated manually for contract lines with a Manual Factor forecasting method.
-
Navigate to Forecasts > Contract Forecast.
-
At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.
-
Click Refresh for screen update.
-
Click the Contract Forecast tab.
-
Type the Manual Factor for the contract lines with Manual Factor forecast method.
-
Click the Save icon.
Manual Factor forecast method calculates the New EAC value using the formula: [AC + ((BAC-EV)/Manual Factor)]. Where AC is actual cost, BAC is Budget at Completion value, and EV is earned value.