Establish Forecast Methods - EcoSys - 2.04 - Help - Hexagon PPM

EcoSys Contracts Help (2.04)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.04

This procedure allows you to establish forecasting methods for each Contract Line. This is required to calculate the Working Forecast.

  1. Navigate to Forecasts > Contract Forecast.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.

  3. Click Refresh for screen update.

  4. Click the Contract Forecast tab.

  5. Click the Forecast Method ellipsis to select the required forecast method. The available forecast methods are listed below:

    • Current Budget

    • Current Forecast

    • Current Productivity

    • Manual EAC

    • Manual ETC

    • Manual Factor

  6. Click the Save icon.

    The columns that contain data used to generate the forecast appears in a green background.