This procedure allows you to delete the link between the tasks or milestones.
-
Navigate to Projects > Project Schedule.
-
At the top of the screen, in the green parameter bar, click the Project ellipsis to select the required project.
-
At the top of the screen, in the green parameter bar, click the Calendar ellipsis to select the required calendar.
The administrator defines calendars which include the time-zone, start time, duration, working days, and non-working days.
-
Click Refresh for screen update. The existing tasks appear on the gantt chart.
-
Double-Click the link between two tasks. The Edit link dialog box appears.
-
Select the Remove this link check box.
-
Click OK. The selected link gets deleted.