This procedure allows you to establish constraint types. Perform any of the following:

  • Setup Constraint Start Date: Follow the procedure below to setup the constraint types for Start Date of the task.

    1. Navigate to Projects > Project Schedule.

    2. At the top of the screen, in the green parameter bar, click the Project ellipsis to select the required project.

    3. At the top of the screen, in the green parameter bar, click the Calendar ellipsis to select the required calendar.

    4. Click Refresh for screen update. The project structure appears in the Project Scheduler panel.

    5. Double-Click the Start Date of the object row. The Edit Start Constraint dialog box appears.

    6. Select the required Start Constraint Type.

    7. Select the required Start Constraint Date.

    8. Click OK.

      To remove the constraint, select the Start Constraint Type as None and click OK.

  • Setup Constraint End Date: Follow the procedure below to setup the constraint types for End Date of the task.

    1. Navigate to Projects > Project Schedule.

    2. At the top of the screen, in the green parameter bar, click the Project ellipsis to select the required project.

    3. At the top of the screen, in the green parameter bar, click the Calendar ellipsis to select the required calendar.

    4. Click Refresh for screen update. The project structure appears in the Project Scheduler panel.

    5. Double-Click the End Date of the object row. The Edit Finish Constraint dialog box appears.

    6. Select the required Finish Constraint Type.

    7. Select the required Finish Constraint Date.

    8. Click OK.

      To remove the constraint, select the Finish Constraint Type as None and click OK.