When you initially create a constraint request, the default status is set to Preliminary because, in most cases, you'll be creating your constraints when planning a project and the actual need date of any constraint resources is not yet known.

When the schedule for the project is determined, you can enter the required need date and submit the request.

In Smart Construction, you can create a new constraint request from multiple locations in the software where you are viewing a list of components. Click one of the following links for details on how to create a constraint when viewing different items:

The ability to create and edit constraints is controlled by access group. For more information on the security requirements for constraints, see Configure security for constraint management.