You can configure the number of threads running on the Smart Construction Scheduler. By default, there are four threads running on the scheduler, used to handle retrieve and the import of any data, such as project configuration or rules of progress.

  1. Log on the SmartPlant Foundation Desktop Client as an administrator.

  2. Click Find > Administration > Schedulers.

  3. In the Find Schedulers dialog box, type the name of the Scheduler, and click OK.

    Smart Construction uses the Smart Construction Scheduler to retrieve data.

  4. Right-click the scheduler in the search results and select Update.

  5. Configure the number of threads in the Max Threads box.