Update the ProgID of the Post Processor rule - Intergraph Smart 3D - Administration & Configuration

Intergraph Smart 3D Project Management

Language
English
Product
Intergraph Smart 3D
Subproduct
Project Management
Search by Category
Administration & Configuration
Smart 3D Version
11 (2016)

When the Post Processor rule compiles with a new ProgID on a project where the IFC was previously using a different Post Processor rule ProgID, or when you modify the ProgID of the IFC rule in the catalog through a bulkload, you must update the ProgID of the Post Processor rule in the model database with an SQL update query.

  1. In the symbol share, locate the new IFC rule DLL.

  2. Open Project Management.

  3. In the Project Management tree, right-click the Interference Server icon , and then click Properties to open the Interference Server Settings Dialog.

  4. On the Database Detect tab, click Stop.

  5. Click Tools > Update Custom Symbol Configuration Command, and select Update Custom Symbol Configuration. See Create or update the custom symbol configuration file.

  6. Bulkload the new Post Processor rule.

    The IFC rule is now defined by the ProgID in the catalog database, but the IFC rule in the model database still refers to the old ProgID.

  7. Right-click the Interference Server icon , and then click Properties to open the Interference Server Settings Dialog.

  8. On the Database Detect tab, click Start to update the ProgIDs.