As a designer, I need to generate the BOM for equipment.
-
As a designer, I need to generate the BOM for instrumentation.
-
As a designer, I need to generate the BOM for piping.
-
As a designer, I need to generate the BOM for structural materials.
-
As a designer, I need to generate the BOM for electrical equipment.
-
As a designer, I need to generate the BOM for HVAC equipment.
-
As a designer, I need to generate the BOM for civil and architectural materials.
-
As a discipline lead, I need to define the work breakdown structure (WBS) per discipline.
-
<decision point> As a discipline lead, I need to check if BOM data is available for the materials for a discipline so that I can receive the BOM data or create a requisition manually.
-
As a discipline lead, I need to manage and analyze for changes the BOM data for the various types of materials and create a material take-off report.
See the work process Manage WBS and BOMs - Level 2 Diagram for more information.
-
As a project stakeholder, I need to define the logic behind how a requisition will be created.
-
As a discipline lead, I need to create or revise the requisition for the project.
-
As a project controls engineer, I need to plan the requisition long-lead items, as decided by the project team.
-
As a discipline lead, I need to complete and validate the requisition for the project prior to submitting for approval or releasing to procurement. This includes:
-
assigning documents
-
assigning VDRs
-
assigning budget
-
defining ROS dates
-
consolidating project control information
-
printing
-
-
As a project stakeholder (engineering managers, project managers, clients, planning engineer, project controls manager, etc), I might review and approve the requisition.
-
As a discipline lead, I need to release the requisition to procurement so that the purchasing process can begin.
See the work process Manage Requisitions - Level 2 Diagram for more information.
-
As a project controls engineer, I need to manage and report on the progress and status of the materials and services.
See the work process Manage Progress and Status - Level 2 Diagram for more information.
-
As a member of the procurement team, I need to procure the necessary materials.