The P6 Connector provides various options for importing and exporting EcoSys and P6 master data. Clients will have their own customized configuration of P6 and EcoSys, so it is necessary to provide flexibility in how master data is integrated between the two systems.

The P6 Connector contains jobs that will easily facilitate integrating one subject area to another.

For example, to import P6 Activity Codes to an EcoSys Task or Transaction Category or exporting EcoSys Cost Object Categories to P6 Project Codes.

Mapping scenarios

For example, if the EcoSys CBS does not match the P6 WBS, then a solution could be configured where a P6 Activity Code is populated with the EcoSys Cost Object structure. This would allow the P6 Scheduler to easily assign the EcoSys CBS to P6 Activities. The P6 Connector then imports the P6 Forecast summarized by this Activity Code under the appropriate CBS element.

During the EcoSys implementation, only the required EcoSys Connect Jobs will be enabled to integrate the desired master data subject areas.

For more information on various P6 master data integration options, see P6 Connector Jobs.