P6 Percent Complete Import - EcoSys - 1.0.01 - Help - Hexagon PPM

Integrating EcoSys with P6 Connector

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Version
1.0.01

The P6 Percent Complete import will update P6 % Complete at the Project and WBS level.

It assumes that the P6 Summarizer process has been run on the P6 Project to have accurate % Complete values.

  • Connect Job: P6 Percent Complete Import

  • EcoSys Action: ITG P6 Percent Complete Import

  • Dependencies: P6 Project and WBS Import

The EcoSys Cost Object External Key field is used to update from the P6 WBS Object ID.

Project level mapping follows the logic described in the section Map an existing EcoSys Project to a P6 Project.

Field Mappings

The default behavior of the % Complete import is to import the following P6 % Complete fields. If required, you can import any available P6 % Complete fields by modifying the Connect Job.

EcoSys Field

EcoSys Subject Area

P6 Field

External Key

Cost Object

WBS Object Id

P6 Budget At Completion Cost

Custom Field (Number)

Summary Budget At Completion by Cost

P6 Earned Value Cost

Custom Field (Number)

Summary Earned Value

P6 % Complete

Custom Field (Percent)

Summary Cost Percent Complete

P6 Performance % Complete

Custom Field (Percent)

Summary Performance Percent Complete