During subcontract work, you must capture deliverables (documentation requirements) so that you can identify late deliverables and analyze performance.
Setup
First, you must enter the statuses for deliverables. Go to P.10.79 Deliverable Status, and enter statuses such as Complete, Open, and In Progress.
Enter a deliverable
-
In the menu tree, navigate to Smart Materials > E&PI(Req) > R.30 Requisitions.
-
Double-click R.30.01 Maintain Requisitions.
-
Query for requisitions.
-
Click Attachments at the lower right.
The software opens D.90.21 Attachments.
On the VDRs tab, you can set the status in the Deliverable Status field (scroll to the right).
-
You can access the deliverables from both the requisition header and line item level.
-
You can also access deliverables from P.30.21, P.30.22, P.50.07, P.70.71, and P.70.72.
-
On P.70.71 and P.70.72, the VDR check box indicates that VDRs are attached. Double-click the check box to display D.90.21.