Conclude a Workshare Collaboration - Intergraph Smart P&ID - Configuration - Intergraph

Intergraph Smart P&ID Workshare Configuration and Reference (2019)

Language
English
Product
Intergraph Smart P&ID
Search by Category
Administration & Configuration
Smart Electrical Version
2019 (9.0)
Smart P&ID Version
9 (2019)
Smart Engineering Manager Version
10 (2019)
  1. Ensure that both host and satellite sites are running the latest Smart P&ID and Smart Engineering Manager service packs.

  2. Satellites transfer ownership of all drawings to the host.

  3. The host gets the latest versions of all drawings.

  4. The host synchronizes shared items. This step cleans up the T_INTERSITEOPC table.

  5. Using Smart Engineering Manager, satellite sites delete satellite plants from their sites. This cleans up the schema users for the plant, plant data dictionary, Smart P&ID, and Smart P&ID data dictionary.

  6. Using Smart Engineering Manager, the host site runs Workshare > Disable Workshare.

  7. The host ensures that all drawings and shared items are owned by the host. For example, open a drawing and, in the plant stockpile, select a loop that was created at the satellite site. Make sure it can be edited. Also, check the Engineering Data Editor to make sure OPC labels match correctly.

  8. The host runs Delete Orphan Model Items > Clean DB.

  • If the satellites do not delete the satellite plants from their sites, orphan data is left behind in their databases, but the host can still disable Workshare.

  • For more information about using the Delete Orphan Model Items utility, see Clean Data Utility (DelOrpModItems.dll) in the Smart P&ID Utilities Help.