Work packages are defined on Work Packages screen as described in Work Packages.

Click on Assigned Work Packages button, to open the Assigned Work Packages screen.

To assign a work package, click Add Row in the Work Packages to Forecast/Reservation Run block, enter a sequence number in the Priority field, and select a pre-defined work package from the LOV in the Work Package field. The other fields in this block and the list nodes in the Work Package Details to Forecast/Reservation Run block are populated automatically from the work package. For the description of the fields, see Work Packages.

The priority determines the order of processing the work packages by the FR.

When an end date is defined for a work package that is assigned to the forecast run, this end date is used during the forecast instead of the end date specified for the forecast run in the Shipment Options section on Create Forecast Run.