Forecast/Reservation Overview - Intergraph Smart Materials - Version 2020 (10.0) - Training - Hexagon

Intergraph Smart Materials Classic Lab Tutorials (2020)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Training
Smart Materials/Smart Reference Data Version
2020 (10.0)

To get a quick overview about forecast and reservation jobs and their reservation status against the BOM, you can use the C.30.21 Forecast/Reservation Overview screen.

With the options at the top of the screen, you can control which FR/RRs appear. The available options are listed below.

Jobs

  • all - Shows all jobs (FR/RRs) of the logged in project.

  • own - Shows only jobs created by the logged in user.

Status

  • issued - Shows all FR/RRs with job status ISSUED.

  • forecasted/reserved - Shows all FR/RRs with job status FORECASTED or RESERVED.

  • all - Shows all FR/RRs independent of the job status.

Type

  • all - Shows all FR/RRs.

  • Forecast Run - Shows only FRs.

  • Reservation Run - Shows only RRs.

The FR/RR name is shown in the Forecast/Reservation Code field, the run number in the Run field, the type in the Type field, and the status of the FR/RR in the Job Status field.

The Split Results indicator is selected if splits exist. The type by which the FR/RR is split is shown in the Split Type field. The Attribute field shows the name of the attribute to be used if the split type was set to Node Attribute or Position Attribute. You can use the Show Splits button at the bottom of the screen to view the split results.

The Allocate Level field defines up to which pre-receiving level the allocation run should look, and this field is only relevant for FRs.

The Shortage field shows the acceptable short quantities for allocating the Bill of Materials as defined with the FR/RR definition. For more information, see Run Options in the Forecast Run Setup section.

The descriptions of the FR/RR header appear in the Short Desc and Description fields.

Click the Show Results button to open the C.30.02 Reserved Nodes screen to check the result of the selected FR/RR. For more information about C.30.02, see Reserved Nodes.

Click the Undo button to reverse the selected FR/RR and to reset all quantities calculated by the FR/RR. The status of the FR/RR is set to REJECTED.