Purpose
This section explains how to assign expediting/inspection events to expediting/inspection levels.
Exercise
-
Open the P.10.57 Events to Levels screen from the Smart Materials > MSCM > P.10 Setup menu branch.
-
Click the Run Query button to display the available levels.
-
Use the scrollbar on the left to scroll to expediting level E-1.
-
Enter 1 in the Seq field in the second block.
-
Click in the Event field.
-
Open the LOV using the List of Values button.
-
Select KOM from the LOV.
-
Select Once from the dropdown list in the Frequency field.
-
Select Order Approval from the dropdown list in the Event Start field
-
In the same way, assign further events to the E-1 level as displayed in the picture below.
-
Save the changes using the Save button.
-
Use the scrollbar in the first block to scroll to the inspection level I-1.
-
Assign events to this level as described above and displayed in the picture below.
-
Close the screen.