May the supplier be changed on a CO?

This project default is used to control whether the supplier can be updated on a change order or not.

If this project default is set to Y (default), a supplier can be changed even on a CO. Please keep in mind that changing the supplier on a CO affects all previous supplements; that is, the complete agreement cycle will be switched to the new supplier.

If this project default is set to N, you can change the supplier on the base (or first) supplement but not on higher supplements of type CO.

  • Module(s) affected by this setting: P5007

  • Default value: Y

  • List of Values: N/Y