Update the progress of work package and work steps - HxGN Smart Build - Version 5.0 U3 (5.0.3) - Help

HxGN Smart Build Insight Help

Language
English
Product
HxGN Smart Build
Subproduct
Insight
Search by Category
Help

Scenario: You notice that the field construction workers completed 75% of a work step in the 00_S_Footings F/R/P work package. Now, you want to update the progress in Smart Build Insight application as well.

  1. Select [Work Package 1] from the list of work packages.

  2. Click the Work Steps tab at the top of the screen to view the list of work steps.

  3. Click the work step that you want to progress. For example: Digital Layout of Formwork.

  4. Select 75% under completion percentage.

    You can see a success message indicating the change is done.

  5. Click X icon on the top left of the Overview screen to close the work steps overview screen.

    The progress of the entire work package is also changed from 0% to 15%.