The percentage of a project that is made up by a step, sub-step, or deliverable. When you create a step or sub-step for a deliverable or assign a deliverable to workpack, you must indicate what percentage of the work that item represents. For example, if a deliverable is 30 percent complete when a particular step is finished, the weighting for that step is 30.