Different revision schemes for plants and projects - SmartPlant Foundation - IM Update 48 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)

It is possible to use one revision scheme for plants and a different revision scheme for projects. To do this, create two revision schemes, one for each level, such as the following:

  • RevA for Config level = 1.

  • RevA1 for Config level = 2.

There is no need to set the Take next major revision on merge property on RevA, because the system automatically does that merging from project to plant, which forces a change in revision scheme. However, setting it does make the intentions clearer.