The WBS information defines the work package, project group, and project number information for SPO/E Core. To make any modifications to these, you must manually modify the DATA_SPO.xlsm file for the WBS.

We recommend that you create a backup copy of the original spreadsheets before making any modifications to them.

Create or modify work packages

  1. Navigate to Smart Community for sample ELF of DATA_SPO.xlsm file. For more information, see Find sample data on Smart Community.

  2. Provide the work package information on the Work Package sheet.

    For example:

    WorkPackage

  3. Click File > Save to save the spreadsheet by renaming it as DATA_SPO_WBS.xlsm.

Create or modify project numbers

  1. Navigate to Smart Community for sample ELF of DATA_SPO.xlsm file. For more information, see Find sample data on Smart Community.

  2. Provide the project number information on the ProjectNumbers sheet.

    Provide the new plant UID wherever applicable.

    For example:

    ProjectNumber

  3. Click File > Save to save the spreadsheet.

Modify the Plant References (Mandatory)

You must modify the plant references to point to the new plant. The mandatory changes are listed below.

  • Make the following modifications to the ProjectNumbers sheet in the DATA_SPO.xlsm file as follows:

    Section

    Columns to be modified

    Description

    SPFConfigurationTree

    UID, UID1

    SPFConfigurationTree data (UID, UID1) associated with the new plant

    For example:

    WBS