To register a tag for progress:

  • Create the tag class (or expand an existing one), and then make the class realize the interfaces that can be progressed. These interfaces are:

    ISPFPrgProgressItem plus either ISPFPrgDesignItem or ISPFPrgActivity.

  • Plan dates must be set during registration. However, only the plan date for the first production step can be entered by the user; the remaining plan dates are calculated based upon the step durations.

  • Actual dates and progress percentages are not enterable.

  • Only the forecast date for the first production step can be entered by the user; the remaining forecast dates are calculated based upon the step durations.

  • When registering multiple activities, they must be of the same deliverable type, and hence share the same review and return periods, and therefore use common step durations.