Change the duration for a workflow step - SmartPlant Foundation - IM Update 48 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)
  1. Right-click the workflow step for which you want to update the duration.

    • You can modify workflow steps in the Edit Workflow Template dialog box when you attach a workflow. Right-click the document to which you want to attach a workflow, and then click Workflow > Attach and Edit Workflow. Click Edit from the Attach and Edit Workflow dialog box.

    • You can also modify workflow steps in the Update Workflow dialog box. Right-click the document for which you want to update a workflow, and click Workflow > Update Workflow.

  2. Click Update Step Duration on the shortcut menu.

  3. Type the new duration for the step, in days.

  4. Use the buttons to select the Target date and Planned date values from the calendar.

    • The Target date value is set and recalculated by the software and equals the start date of the step plus the step duration. This date is the date when overdue management and step expiration are initiated.

    • The Planned date is not recalculated automatically when the duration is changed. However, you can modify either date manually from the Update Step Duration dialog box.

    • The Planned date value can be used within reports to plan work.