Initiate Replan dialog box - SmartPlant Foundation - IM Update 48 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)

Allows you to initiate a replan for any level in the hierarchy, down to individual workpacks. All deliverables in each affected workpack are put into Replan mode, meaning that only the Replan dates can be modified.

The default replan dates are based upon the Actual dates provided for steps. If an Actual date does not exist for a step, the replan date will be based on the forecast date of the step. If a step has no forecast date, the replan date is based on the plan date. 

These dates must fall within their Replan Start and End dates for the workpack.

Contract - Specify the contract.

Area - Specify the top level of the hierarchy for which you want to initiate a replan.

Unit - Specify the second level of the hierarchy for which you want to initiate a replan.

See Also

Configure replan