Some of the project defaults must be set before any MRR can be created. Others are optional depending on the detailed workflow established by the project.

Project Default

Comment

ZC_AUTO_RR

With this project default, you can control the behavior of the Material Issue Report (MIR) when there are differences between reserved and issued quantities. If the project default is set to N, no new reservation run is generated either because of deleted positions or changed issue quantities when a MIR is posted. If the project default is set to Y, new reservation run(s) are generated for outstanding positions and quantities when a MIR is posted.

ZC_BESTQTY

This project default controls the setting of the BOM Best Qty uses only Site Status check box.

ZC_BIN_LOC

This project default controls if warehouse logic is used (ZC_BIN_LOC=WHTU, default), or if bin location logic is used (ZC_BIN_LOC=BLOC).

ZC_C2022ST

This project default defines the sort option for the list of inventory items on MIR by BOM Commodity (Window 2). This list can be sorted by specifying one of the possible parameter values from the LOV. The values for this sort option have the form of, for example: BOM/IDENT/TAG, which means that the list is first sorted by BOM (that is, list node, BOM position number), then by ident code, and then by tag number. Other possible sort options are:

  • BOM/TAG/IDENT

  • IDENT/BOM/TAG

  • IDENT/TAG/BOM

  • TAG/BOM/IDENT

  • TAG/IDENT/BOM.

ZC_C2023A1

With this project default, you can assign an attribute with the corresponding user defined LOV to the Attr1_value field in the Inventory Issues block of the MIR by Direct Issue screen.

ZC_C2023A2

With this project default, you can assign an attribute with the corresponding user defined LOV to the Attr2_value field in the Inventory Issues block of the MIR by Direct Issue screen.

ZC_C2023A3

With this project default, you can assign an attribute with the corresponding user defined LOV to the Attr3_value field in the Inventory Issues block of the MIR by Direct Issue screen.

ZC_MIRAPPR

This project default is used for the material issue report (MIR) approval process. If an approval template is assigned to ZC_MIRAPPR, MIRs can only be posted if all users of the approval sequence have approved the material issue report on the Approval Process screen.

ZC_MULT_WH

This parameter is used for general warehouse selection for BOM Issue and Direct Issue. On Warehouses, you can select the warehouses you want to see in inventory issues, but only the warehouses assigned to the user on Warehouses to Users.

ZC_PROJSUB

You can define a project subcontractor list for the current project on the Project Subcontractors screen. If you set this project default to Y, you can select subcontractors only from the project subcontractor list that is defined for the current project.

ZC_QTYISS

If you set this project default to N, the issue quantity is filled with 0 (zero) by default in the issue screens. If the project default is set to Y (default), the issue quantity is filled with the required quantity or the on-hand quantity.

ZC_REV_ALL

If this project default is set to Y, all inventory issues from the previous MIR revision are included automatically when you click the Revision button on MIR By Reservation, MIR By BOM Commodity, MIR by Direct Issue, MIR by BOM Ident Screens. On the highest revision of a MIR, all actual values for the MIR appear. Only the changed lines are revised and posted to the inventory.

ZC_SCRAP_M

This project default is used to attach an mv_where view to control the idents that are transferred into a scrap warehouse. If this default is set and a scrap warehouse is entered on the issue screens, overissued materials that match the mv_where view is transferred into the scrap warehouse.