In Structural module, you must first load the weld components in Administration > Weld Components module and then load the structural welds in the Structural > Welds module. After the welds are loaded, they undergo the following stages of inspection to check the quality of a weld.
-
Material Verification
-
Fit-Up Verification
-
Material Verification + Fit-Up Verification
-
Pre weld Heat Treatment
-
Visual Inspection
-
Non-Descrutive Testing BSR
-
Ultrasonic Testing (UTE)
-
Hardness Testing (HDT)
-
Radiography Testing (RTE)
-
Positive Material Identification Testing (PMI)
-
Magnetic Particle Inspection Testing (MPI)
-
Ferrite Count Testing (FCO)
-
Dye Penetrant Inspection Testing (DPI)
-
Phase Array Ultrasonic Testing (PAU)
-
Post Weld Heat Treatment (PWHT)
-
Time of Flight Diffration (TOFD)
-
-
Post Weld Heat Treatment Inspection
-
Non-Descrutive Testing (ASR)
-
Ultrasonic Testing (UTE)
-
Hardness Testing (HDT)
-
Radiography Testing (RTE)
-
Positive Material Identification Testing (PMI)
-
Magnetic Particle Inspection Testing (MPI)
-
Ferrite Count Testing (FCO)
-
Dye Penetrant Inspection Testing (DPI)
-
Phase Array Ultrasonic Testing (PAU)
-
Post Weld Heat Treatment (PWHT)
-
Time of Flight Diffration (TOFD)
-