File > Import > ScheduleReview Project

Imports an existing SRI file into the current project database. You can also import a selected ScheduleReview project from a different Smart Review project database into the current project database. This imported and manipulated ScheduleReview information can then be exported to a Smart Review project database file.

  1. Click File > Import > ScheduleReview Project.

  2. On the Open dialog box, select a file or browse to the file, and click Open.

  • Smart Review does not verify the fitness of use for any type of data that you import or export between project databases. Smart Review assumes that all projects used during import or export activities contain equivalent model space and unit settings. Therefore, it is possible to import or export project data that is not relevant to the project that receives the data.

  • The project that you import must have a unique name. You can import an existing SRI file into the current project database. You can also import a selected ScheduleReview project from a different Smart Review project database into the current project database. This imported and manipulated ScheduleReview information can then be exported to a Smart Review project database file.

  • When you import an existing SRI file from a previous ScheduleReview session, ensure that all ScheduleReview settings have a valid option selected.

  • To avoid error messages that may occur when you open an existing SRI file created with MS Project Planner, open the MS Project Planner file in MS Project.

  • You can see a list of projects by expanding the ScheduleReview node in Project Manager.

See Also

ScheduleReview Animations
Set the Active Project
Export ScheduleReview Projects