If a more precise shift planning than calendar capacity for a work place is needed, the Work Plans can be added. Work Plans display shows the work places using shift calendars.
The selection Show in Work Plan for the calendar must be selected for using this feature. The selection is set on Work Place Capacity tab and section tab Settings.
Only one work plan can be valid for a certain period. If work plans are changed, the capacity must be updated by clicking the Update Capacities button. The warning sign in the tree branch shows work plans that have been modified without updating the capacity afterwards.