  1. In Drawing Manager, click Workshare > Synchronize Reference Data.

  2. When the synchronization process finishes, click Close.

  3. Exit, then re-open Drawing Manager. You can now publish or get the latest version of drawings.

  • In order to synchronize the databases, the DBLink or other network connection between host and satellite must be active.

  • You can view the progress of the synchronization process on the Synchronize dialog box.

  • If a satellite does not synchronize reference data, the satellite can neither publish nor get the latest version of a drawing.

  • For information about synchronizing reference data without a remote connection to the host, see Synchronize Reference Data from a Copy.