This scenario represents the following changes to the ABE data:
-
Stream Flow Rate property updated for both streams
-
Pump Capacity property updated for the ABE equipment source item
-
NumberRequired value increased from 2 to 3
These changes will result in the generation of the following To Do List tasks:
-
2 Update tasks for existing pumps P-101A and P-101B
-
2 Update tasks for pipe runs
-
1 Create task for new pump P-101C
-
Display the To Do List dialog for imported ABE data (equipment and streams):
-
Select the 5 new tasks in the list (four Update tasks and one Create task) and select the Run command.
-
From the EDE item list, select Equipment: Mechanical.
The new pump assembly P-101C appears in the Active Drawing Stockpile.
-
Select P-101C in the EDE and drag it to the Design Window to the position where you want to place it.
-
Click to place the assembly.
-
Select the main item of each assembly to view its properties and note the changed value for Pump Capacity.
-
Select each pipe run in turn to view its properties and note the changed value for Stream Flow Rate.