PPM All Outputs Graphic

Enables you to check drawings into the Plant. This command is available only when drawings are selected in the List view and when those drawings are checked out to the current project. Drawings created in a project automatically belong to that project and can be selected and checked in. This command is not available from within the Plant.

  • You must have the correct permissions, assigned in Smart Engineering Manager, before you can check drawings in or out.

  • You cannot check a drawing in if any of the objects that belong to that drawing were modified after the latest version of a drawing was created. For more information about creating versions, see Save a Version of a Drawing.

  • If an invalid claim is found but the item in question matches the item in the Plant, run Verify for Checkin to resolve this situation. This process automatically sets the claim to valid and allows the check in to occur.