  1. To open the SOW Milestone window, click Maintain Requisitions > SOW Milestone.

  2. Select a date in the Start Work cell.

  3. Select a date in the Substantial Completion cell

  4. Select a date in the Final Completion cell.

  5. Select an activity from the Start Activity list.

  6. Select and activity from the Substantial Activity list.

  7. Select an activity from the Final Activity list.

  8. In the Interim Milestones section, click Add Row to maintain the SOW Milestone details.

  9. Type a unique number in the Seq cell and a description in the Interim Milestone cell.

  10. Select the Activity Code from the list.

  11. Select a date in the Date cell.

This page is only available for subcontracting inquiries or requisitions.