This project default specifies whether only one Over Short and Damaged (OSD) per MRR number is allowed.
If you switch the project default from N to Y even though the OSDs are already created, and you cannot create further OSDs on the Warehouse Management > Material Receiving page, use the Warehouse Management > OSDs page instead.
-
Module(s) affected by this setting: Material Receiving by Agreement, Direct Receive, Release Notes, and Package.
-
List of Values: Y and N (default).
-
If set to Y, the number of OSDs that can be created for material receiving are restricted to one OSD per MRR.
-