This project default sets the default commodity part for the tagged items in the E&PI(BOM/Req) module. When a tagged item is created in the BOM, you can choose the group/part under which this new tag gets created. If no group/part is selected, the part that is selected in this project default is the part where the new tag is created.
-
Module(s) affected by this setting: Maintain BOM, Position Details, Advanced Search, Search Results, Procedures/Macros, BOM Procedures/Macros Logs, BOM Import, BOM Import Job Details, BOM Import Protocol, Review Data, Run Procedures, MRR by Agreement, MRR by Release Notes, MRR by Package, P3022, P3027, Procurement > Agreements, Expediting, Requisitions > Maintain Requisitions.
-
Default value: ./.
-
List of Values: Commodity Parts.