For scheduling the scope of work (SOW) covered by this inquiry, you can define SOW milestones.
SOW Milestones is only available for inquiries of type Subcontract.
-
Click Prepare RFQ > SOW Milestones.
-
Enter the start date of the start activity in the Start Work box.
-
Select the Start Activity from the list.
-
Enter the completion date of the substantial activity in the Substantial Completion box.
-
Select the Substantial Activity from the list.
-
Enter the completion date of the final activity in the Final Completion box.
-
Select the Final Activity from the list.
-
To add interim milestones, click Add Row and do the following.
-
Type a unique sequence number in the Seq cell.
-
Type the Interim Milestone description.
-
Optionally, select an Activity Code from the list.
-
Select the scheduled Date for the milestone.
-
Click Save.
-
To delete the SOW milestones with all details, click Delete.