Sorting the positions means that all requisition line items are ordered by commodity code, size 1, and size 2. Moreover, the Pos and Sub fields are updated; Pos is filled in ascending order by a sequence with an increment of 1, and Sub is filled with 1.
-
Click Sort Position to sort the requisition line items.
-
The button is only enabled if:
-
You are logged in with the discipline of the engineering requisition,
-
The requisition has been created manually,
-
The requisition has not been approved yet.
-
-
If the project default ZR_SORTPOS is set to N, the Sort Pos button will be disabled for requisition supplements greater than 0 (zero).