Item Progress - Intergraph Smart Materials - Version 10.1 - Help - Hexagon

Intergraph Smart Materials Web Help (10.1)

Language
English
Product
Intergraph Smart Materials
Subproduct
Web
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.1
  1. On the Home page, click Subcontract Management> Subcontractor Workload.

    If the payment type for the agreement is Measured Quantity, you can go to the Item Progress tab for information about the period progress numbers.

  2. To track measured quantity item progress, click the Item Progress tab.

    • The ZP_APRWKP project default must be set in order to notify others (by e-mail) about submitted progress items. You can assign this project default to an approval template of type Work Progress.

    • The current user must have the PROGRESS APPROVAL privilege in order to approve progress or reverse approval.

  3. To approve the process for progress items, click Approval Sequence.

  4. To reverse the approval, click Reverse Approval.

    All approvals in the approval sequence are removed, and the approval sequence must be re-started.

  5. To submit the item progress, click Submit.

  6. To allow a contractor to request the re-submission of a progress item before the approval sequence has been started, click Request Resubmit.

    As soon as any of the approvers has approved or rejected, the Request Resubmit button becomes unavailable.

  7. Click Delete Row to delete an item progress.