  1. For Purchase :This check box indicates whether the line items of this engineering requisition can be used for both purchase orders and inquiries or only for inquiries.

    1. If this checkbox is not checked the engineering requisition can only be used for inquiries.

    2. This checkbox is part of the unique key to have the possibility to separate the resulting engineering requisitions.

    3. It is important in the procedure which creates supplements of an engineering requisition: An engineering requisition with the same name (CODE) and origin has supplement 0 (zero) if it is the first one with indicator set to 'Y' (checkbox checked) or 'N' (checkbox not checked).

    4. If procurement has already created requisitions for purchase based on the results of an inquiry cycle (via the Commercial Evaluation page) you can only continue with creating supplements for inquiry only requisitions. In this case requisitions for purchase cannot be created by an MTO job. After the inquiry only requisition supplements have been created and released to procurement it is up to procurement to either create the corresponding (not approved or released) requisition supplements for purchase or to go through another inquiry cycle for new line items.

    5. This restriction is not only valid for the actual MTO type itself but also for its parent type.

    6. Project default ZR_M_PURCH contains the default value for this field.

  2. Technical Evaluation Required: This check box is used to indicate whether the MTO job is required to set a technical evaluation on all requisition line items created by this job depending on the CIP procedure tech_eval(r_id).

    1. If the checkbox is checked, then the Technical Evaluation Required cell on requisition line items are set to no as default value or to the value of the previous requisition respectively.

    2. If the checkbox is unchecked, then the CIP procedure is used to determine those line items that require a technical evaluation.

    3. If you insert a new record the value of project default ZR_M_TEVAL is taken as default value.