  1. As a materials discipline lead, I need to define the BOM structure, views, and attributes.

  2. As a materials discipline lead, I need to define and maintain the loading templates.

  3. As a materials discipline lead, I need to set up the revision control criteria so that Smart Materials will maintain BOM data for each revision imported.

  4. As a project control engineer or project planner, I need to create project control and planning break down structure to define the common structure of the asset and reconcile information across various tools and departments.

  5. As a materials discipline lead, I need to define or verify the work breakdown structure (WBS) per discipline so that BOM data can be allocated against the correct node.

  6. <decision point> Is BOM data to be entered manually?

  7. As a materials engineer, I need to define the BOM data manually using Smart Materials to create data that cannot currently be imported from other tools. This event might occur on a regular basis during the length of the project reflecting the development of the design, if necessary.

  8. As a materials engineer, I need to assign and verify the revision of the BOM data so that Smart Materials can automatically compare all different revision statuses coming from any tool.

  9. As a schematics designer, I need to extract BOM data from SmartPlant Enterprise schematics tools. This event will occur on a regular basis during the length of the project reflecting the development of the design.

  10. As a 3D designer, I need to extract BOM data from 3D tools (Intergraph Smartâ„¢ 3D and PDS). This event will occur on a regular basis during the length of the project reflecting the development of the design.

    Flag graphic for work process references See the following Integration Capability Statement for more information:

    • Creating Isometrics with SmartPlant Isometrics for Documentation and Fabrication

  11. As a fabricator, I need to extract BOM data from SmartPlant Spoolgen. This event will occur on a regular basis during the length of the project reflecting the development of the design.

    Flag graphic for work process references See the following Integration Capability Statement for more information:

    • Creating Pipe Spools for Procurement, Fabrication, and Construction

  12. As a designer, I might extract BOM data from any non-SmartPlant Enterprise design tool for any discipline. This event might occur on a regular basis during the length of the project reflecting the development of the design.

  13. As a fabricator, I might extract BOM data from a non-SmartPlant Enterprise fabrication tool, such as Tekla. This event might occur on a regular basis during the length of the project reflecting the development of the design.

  14. As a designer or materials engineer, I might develop BOM data in another application, such as a spreadsheet or text file tool. This event will occur on a regular basis during the length of the project reflecting the development of the design.

  15. As a materials engineer, I need to import the BOM data against a specified revision. Each revision might be used for engineering and requisition where specific revisions would be used for construction purposes. During import, Smart Materials automatically compares the different revisions of the BOM data.

  16. As a materials engineer, I need to verify the BOM data, adjusting it as needed so that the BOM data is complete, correct, and ready for use in downstream processes.