Define a Forecast Run - Intergraph Smart Materials - Version 2020 (10.0) - Training - Hexagon

Intergraph Smart Materials Classic Lab Tutorials (2020)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Training
Smart Materials/Smart Reference Data Version
2020 (10.0)

Purpose

This section explains how to define a forecast run to simulate materials availability.

Exercise

  1. Open the C.30.01 Forecast Run screen from the Smart Materials > Site > Field Material Control > C.30 Construction Planning menu branch.

  2. Click Cancel Query to switch to new record mode.

  3. Enter FR-TRAIN01 in the Forecast Code field.

  4. Enter FR-Training1 in the Short Desc and Description fields.

  5. Select the status 0 from the LOV in the List Status field.

  6. Save the changes using the Save button.

  7. Open the Fastcall menu in the upper right corner.

  8. Select C.30.01.01 Assigned Warehouses from the menu.

  9. Enter 1 in the Seq field.

  10. Select STORE from the LOV in the Warehouse field.

  11. Save the changes using the Save button.

  12. Close the screen.

    You return to C.30.01.

  13. Open the Fastcall menu in the upper right corner.

  14. Select C.30.01.02 Assigned Work Packages from the menu.

  15. Enter 1 in the Priority field.

  16. Select the pre-defined WP-PIPING from the LOV in the Work Package field.

  17. Save the changes using the Save button.

    The BOM list nodes assigned to the selected work packages appear in the lower block.

  18. Close the screen.

    You return to C.30.01.