This section explains how to set the relevant project defaults when working with agreements in a new project in the Smart Materials MSCM module.

Exercise

  1. Open the A.20.12 Projects Defaults screen from the Administration > A.20 Project/Product Group menu branch.

  2. The login project should appear in the first block. If not, click the Enter Query button to change to query mode, open the LOV using the List of Values button, and select the project from the list. Then click OK to close the LOV. Click the Run Query button to display the selected project with its details.

  3. Click the MSCM tab to display the project defaults relevant for the Material Supply Chain Management module.

  4. Double-click in the Value field of project default ZP_ADV_APP, and select Y from the LOV.

  5. Double-click in the Value field of project default ZP_APRPO, and select TRAIN-PO/P from the LOV.

  6. Double-click in the Value field of project default ZP_RM_MAND, and select Y from the LOV.

  7. Double-click in the Value field of project default ZP_PORANG, and select PO-RG-01 from the LOV.

  8. Click in the Value field of project default ZP_PORULE, and enter ‘#PROJECT#-PO-#ZP_PORANG#’.

  9. Save the changes using the Save button.

  10. Close the screen by selecting File > Close All or Close from the main menu.