This section explains how to define and run MTO jobs.

Exercise

  1. Open the R.20.01 MTO Jobs screen from the Smart Materials > E&PI (Req) > R.20 Material Take Off menu branch.

  2. The first (MTO Types) block displays the predefined MTO types. You must select the appropriate type to be used for the MTO job. In our example, just the PIPING MTO type is available.

  3. Enter ā€˜PIP-001ā€™ as the name of the new job in the Job field of the second (MTO Jobs) block and ā€˜1st MTOā€™ in the Short Desc and Description fields.

  4. Click in the Min. List Status field, and open the LOV using the List of Values button, select 00-DEF from the list, and click OK to complete the selection.

    All other fields are either optional or are preset according to the setting of the related project defaults.

  5. Click the Save button to save the changes.

  6. Click the button in the Job Control Section in the lower right corner to launch the MTO job.

    If the job was successful, a message appears informing you about the job result, as displayed in the picture below.

  7. Click OK to complete the job.

  8. In case of an error, you can use the button to open the A.60.72 Show Log file of MTO Job screen. Here you can check the log file to find the reason for the problem.

    Click the in the upper right corner of this screen to close A.60.72 and go back to R.20.01.

  9. Click the button to open Window 2 where BOM positions that were NOT handled by the MTO job are displayed.

    If all settings were made correctly as described in the previous chapters, the screen should not show any positions as displayed in the picture below.

  10. Close the screen by selecting File > Close All or Close from the main menu.

  11. Open the R.30.01 Maintain Requisitions screen from the Smart Materials > E&PI (Req) > R.30 Requisitions menu branch. The screen opens in enter query mode; all fields are displayed with a yellow background.

  12. Click the Run Query button to display the requisitions created by the MTO job.

  13. Scroll to the right to display the MTO job related information.

  14. Double-click the requisition name in the Engineering Requisition field to open Window 2, which displays the requisition line items.

    In the New List Quantity field, you find the summarized quantity for the selected ident found by the MTO job on all BOM positions considered by the job.

  15. Close the screen by selecting File > Close All or Close from the main menu.