Quantity Calculation Options - Intergraph Smart Materials - Version 10.2 - Help - Hexagon

Intergraph Smart Materials Classic Help

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2

The Scope Of Interest field is used to define which quantities are to be generated in a requisition. The available options are:

  • All Quantities (+, -, and unchanged)

  • Shortage Quantities (only + quantities)

  • Surplus Quantities (only - quantities)

The default value for this option is defined by the project default ZR_M_SOI.

SHARED Tip On the R.30.01 screen, the user can set the display option Release Context. This field also allows displaying only shortage, only surplus, or all quantities. To be able to use this feature on R.30.01, the Scope Of Interest option must be set to ‘All quantities’.

The disposition procedure uses the calculated quantity for a line item (New List Quantity) to calculate an optimized quantity value, based on rules assigned to the material.

The logic (dispo rule), the way the disposition will be processed, must be selected from the dropdown list in the Dispo Rule field. It can vary between two MTO jobs of the same MTO type and must be entered before the MTO job will be started.

The four dispo options that are available in the Dispo Rule field are as follows:

Dispo Option

Purpose

Common Rule

The MTO job will use the Dispo Rule specified in the template.

Fix Dispo Addend

This calculates recommended quantity (and hence Dispo quantity) as equal to the greater of either the current Recommended Quantity or the previous supplement Released Quantity. This option avoids unnecessary qty changes on POs if the dispo quantity is not considered overly important.

Fix Dispo Quantity

Dispo quantity remains the same as the previous supplement.

None

No disposition (contingency) material. This option will also disable the dispo rule specified in the template.

It is important to understand the different quantity fields on a requisition line before selecting the correct dispo rule option. The fields are listed below.

Field

Purpose

New List Quantity

Total quantity on the current (new) BOM.

Released Quantity

Quantity that is released to procurement; by default, it initially equals the Recommended Quantity. This field may be edited manually by the user to change the contingency material.

Recommended Quantity

The New List Quantity plus the dispo (contingency) material.

The default value for the Dispo Rule field is defined by the project default ZR_M_DISPO.

Select the Set Increased Quantity Factor option to let the MTO job calculate the increased quantities based on the previous requisition supplement. When the indicator is not checked, the increased quantity field in the requisition will not be calculated. It must then be manually verified by an engineer and set before the requisition can be released to procurement. This is a way to force the engineers to check the increased quantity rather than simply accepting the calculation done by the MTO job. The default value for this option is defined by the project default ZR_M_I_QTY.

A BOM node may have a quantity factor set in its definition on B.20.01; see example in the picture below.

If the List Node Factor indicator is selected, the calculated quantity will be multiplied by this qty factor. If it’s not checked, the factor will be ignored. The default value for this option is defined by the project default ZR_M_LNFCT.

Select the Handle Assemblies indicator to explode assemblies (that are found on the BOM) into their component parts and include the individual components in the total quantity instead of the assembly quantity. The default value for this option is defined by the project default ZR_M_ASSEM.