ZP_EXPDATE - Intergraph Smart Materials - Version 2020 (10.0) - Administration & Configuration - Hexagon PPM

Intergraph Smart Materials Classic Administration (2020)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Administration & Configuration
Smart Materials/Smart Reference Data Version
2020 (10.0)

Update/Calculation of some expediting dates.

The setting of this project default affects the changeability of the promised contract and promised ship date and the automatic calculation of the predicted on site date in expediting.

If this project default has been set to Y (default), promised contract and promised ship date can only be changed in screen P.50.07 before an order is approved. These dates cannot be modified later on by expediting (screens P.70.xx).

The predicted on site date is filled with the promised ship date plus the number of transit days when an item shipment is created.

Only in case of using basic expediting (ZP_NEW_EXP set to N), the predicted on site date is updated automatically on modification of any of the following data:

  • Curr/Rev Prom Ship date

  • Pred Ship date

  • Actual Ship date

  • Routing Method

  • Carrier Name

In each case, the new predicted on site date is calculated as Modified date + transit days.

The number of transit days is determined by the routing method of an item shipment.

If this project default has been set to N, promised contract and promised ship date can also be changed by expediting after the order has been approved.

The predicted on site date remains empty when an item shipment is created and is not automatically filled if any other date field is modified.

  • Module(s) affected by this setting: P3002, P3004, P5001, P5007, P7021, P7031, P7061, P7062, P7072, OPI1001

  • Default value: Y

  • List of Values: N/Y