Project default ZP_MS_SFAD is used to choose between two options of how the forecast calculation handles forecasted dates of milestones where an actual date is present.
With the default value Y in place, forecasted dates are synchronized with the respective actual dates (unless a forecasted date appears to be locked) during forecast (re-)calculation, this is, for each milestone where an actual date is present this date value will be taken over to its forecasted date.
Set ZP_MS_SFAD to N in case you prefer to preserve the original forecasted date of a milestone when it is provided with an actual date. There is no need to lock the forecasted date prior to entering the actual date when this option is chosen.
-
Module(s) affected by this setting: Planning, P6001, P6003, P6005
-
Default value: Y
-
List of Values: N/Y