CO number unique.

This parameter defines how the number of a change order is created when either choosing the Create Supplement option on P.30.01 or when clicking Create CO on P.50.07.

If the parameter is set to N (default), the number of the corresponding order (purchase order, notice of commitment or blanket order) is just taken over.

If the parameter is set to Y, the number of the corresponding order is taken over, too. But this number is enlarged by the supplement of the order and a number showing how many change orders exist for this order at the moment of the creation of the CO.

Example:

The number of the order is PO-100-PIPE, supplement 3.

The first change order that is created for this order will get the number PO-100-PIPE 3 1. The second change order will have the number PO-100-PIPE 3 2.

Change orders for supplement 5 of the order PO-100-PIPE will get the numbers PO-100-PIPE 5 1, PO-100-PIPE 5 2 and so on.

This project default has no effect if CIP m_pck_po_custom.gen_order_number does not return NULL values.

  • Module(s) affected by this setting: P3001, P3002, P3004, P5007

  • Default value: N

  • List of Values: N/Y