This project default specifies whether to add the manual line item quantity to the MTO line item quantity (with the next MTO).

The following parameters decide whether the check box on R.10.41 Manual to MTO line item is checked or not when starting the form (of course this can be changed manually):

Y => Check box is checked

N => Check box is not checked

If the check box is checked, the software tries in the next MTO run to integrate a manual line item into an MTO line item. This will only be if the manual line item data exists on the BOM.

  • Module(s) affected by this setting: R1041, R2001

  • Default value: N

  • List of Values: N/Y