ZP_CHK_PPE - Intergraph Smart Materials - Version 10.1 - Administration & Configuration - Hexagon

Intergraph Smart Materials Classic Administration (10.1)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Administration & Configuration
Smart Materials/Smart Reference Data Version
10.1

Check remaining residual costs on the Prog Pay Events tab before approving a purchase order (PO).

With this project default, you can control whether residual costs are checked on P.50.07 Maintain Agreements, Prog Pay Events tab, when approving a PO.

If ZP_CHK_PPE is set to Y (default), the PO cannot be approved if residual costs are remaining.

If ZP_CHK_PPE is set to N, no check of the residual costs is performed when approving a PO. If the agreement total costs change, the progress payment event cost values are automatically recalculated.

  • Module(s) affected by this setting: P5007

  • Default value: Y

  • List of Values: N/Y